Difference between revisions of "Circuit Failure Mode Likelihood Analysis (Task 10)"

From FirePRA
Jump to navigation Jump to search
Line 8: Line 8:
  
 
# Fire PRA cable selection ([https://firepra.epri.com/index.php?title=Fire_PRA_Cable_Selection_(Task_3) Task 3]),
 
# Fire PRA cable selection ([https://firepra.epri.com/index.php?title=Fire_PRA_Cable_Selection_(Task_3) Task 3]),
# Detailed circuit failure analysis (Task 9), and
+
# Detailed circuit failure analysis ([https://firepra.epri.com/index.php?title=Detailed_Circuit_Failure_Analysis_(Task_9) Task 9]), and
 
# Circuit failure mode likelihood analysis (Task 10).
 
# Circuit failure mode likelihood analysis (Task 10).
  

Revision as of 09:44, 6 November 2018

Task Overview

Background

This task considers the relative likelihood of various circuit failure modes. This added level of resolution may be a desired option for those fire scenarios that are significant contributors to the risk. The methodology provided in this document benefits from the knowledge gained from the tests performed in response to the circuit failure issue.

Purpose

Conducting a Fire PRA in accordance with this methodology necessitates an analysis of fireinduced circuit failures beyond that typically conducted during original Fire PRAs. The circuit analysis elements of the project are conducted in three distinct phases:

  1. Fire PRA cable selection (Task 3),
  2. Detailed circuit failure analysis (Task 9), and
  3. Circuit failure mode likelihood analysis (Task 10).

This task provides methods and instructions for conducting the third phase of circuit analysis – circuit failure mode likelihood analysis for Fire PRA cables. Task 10 estimates the probability of hot short cable failure modes of interest, which in turn can be correlated to specific component failure modes. As discussed in Section 3.3.2 of Volume 1, the methods and techniques for deriving circuit failure mode probability estimates are based on limited data and experience. Consequently, this area of analysis is not yet a mature technology, and undoubtedly further advances and refinements will come with time. Nonetheless, the methods and techniques presented in this chapter represent the current state of knowledge and provide a reasonable approach for establishing first-order circuit failure mode probability estimates, albeit with relatively high uncertainty tolerances.

Scope

Chapter 10 provides methods and technical considerations for assigning probability estimates to specific cable failure modes associated with fire-induced cable damage.

This task does not address the implementation of plant-specific quality assurance or configuration control requirements that might apply to a Fire PRA. Nor is it intended to validate the accuracy of plant-specific data extracted from plant drawings, documents, or databases. Each plant should follow appropriate quality assurance, administrative, and configuration control procedures applicable to the work being conducted. The need to validate input source documents should be addressed as part of assembling the prerequisite information in Step 1.

Related Element(s) of ASME/ANS PRA Standard, ASME-RA-Sb-2013

Circuit Failures (CF)

Related EPRI 1011989 NUREG/CR-6850 Appendices

Appendix J, Appendix for Chapter 10, Technical Basis for Circuit Failure Mode Likelihood Equations

Appendix K, Appendix for Chapter 10, Examples of Component Circuit Failure Mode Likelihood Analyses

Supplemental Guidance

Since the publication of NUREG/CR-6850, significant research on fire-induced spurious operations has occurred. EPRI 3002001989 / NUREG/CR-7150 Volume II revises a significant portion of Task 10 of EPRI 1011989 / NUREG/CR-6850.

Joint Assessment of Cable Damage and Quantification of Effects from Fire (JACQUE-FIRE): Phenomena Identification and Ranking Table (PIRT) Exercise for Nuclear Power Plant Fire-Induced Electrical Circuit Failure (EPRI 1026424 / NUREG/CR-7150 Volume 1)

This report documents a Phenomena Identification and Ranking Table (PIRT) exercise on fire-induced electrical circuit failures that may occur in nuclear power plants as a result of fire damage to cables. The results and conclusions of the PIRT panel are a primary input to the follow on PRA Expert Panel documented in Volume 2.