==Task Overview==
 
==Task Overview==
 
===Background===
 
===Background===
This task identifies fire analysis compartments that can be shown to have little or no risk significance without quantitative analysis. Fire compartments may be screened out if they contain no components or cables identified in Tasks 2 and 3, and if they cannot lead to a plant trip due to either plant procedures, an automatic trip signal, or technical specification requirements.
+
This task identifies fire compartments that can be shown to have little or no risk significance without quantitative analysis. Fire compartments may be screened out if they contain no components or cables identified in Tasks 2 and 3, and if they cannot lead to a plant trip due to either plant procedures, an automatic trip signal, or technical specification requirements.
  
 
===Purpose===
 
===Purpose===
This procedure describes the criteria for qualitatively screening the fire compartments defined in Task 1.  
+
This procedure describes the criteria for qualitatively screening fire compartments defined in Task 1.
  
 
===Scope===
 
===Scope===
This work package addresses the following issues in qualitative screening:
+
This task addresses the following issues in qualitative screening:
  
 
* Definition of screening criteria and basis, including definition of plant trip initiator and controlled manual shutdown;
 
* Definition of screening criteria and basis, including definition of plant trip initiator and controlled manual shutdown;
 
* Reference to Fire PRA component list used in qualitative screening and criteria for equipment selection; and
 
* Reference to Fire PRA component list used in qualitative screening and criteria for equipment selection; and
  
In most fire IPEEE analyses, the primary containment was qualitatively screened. In this methodology description, the examination of potential risk associated with fires in primary containment will follow steps similar to other locations of the plant.  
+
In most fire Individual Plant Examination of External Events (IPEEE) analyses, the primary containment was qualitatively screened. In this methodology description, the examination of potential risk associated with fires in primary containment will follow steps similar to other locations of the plant.
  
==Related Element(s) of ASME/ANS PRA Standard, ASME-RA-Sb-2013==
+
==Related Element of ASME/ANS PRA Standard==
 
+
Qualitative Screening (QLS)
 
 
==Related NUREG/CR-6850 Appendices:==
 
  
 +
==Related EPRI 1011989 NUREG/CR-6850 Appendices==
 +
None
  
 
==Supplemental Guidance==
 
==Supplemental Guidance==
 +
There is no supplemental guidance associated with Qualitative Screening (Task 4).

Latest revision as of 15:16, 10 December 2018

Task Overview

Background

This task identifies fire compartments that can be shown to have little or no risk significance without quantitative analysis. Fire compartments may be screened out if they contain no components or cables identified in Tasks 2 and 3, and if they cannot lead to a plant trip due to either plant procedures, an automatic trip signal, or technical specification requirements.

Purpose

This procedure describes the criteria for qualitatively screening fire compartments defined in Task 1.

Scope

This task addresses the following issues in qualitative screening:

  • Definition of screening criteria and basis, including definition of plant trip initiator and controlled manual shutdown;
  • Reference to Fire PRA component list used in qualitative screening and criteria for equipment selection; and

In most fire Individual Plant Examination of External Events (IPEEE) analyses, the primary containment was qualitatively screened. In this methodology description, the examination of potential risk associated with fires in primary containment will follow steps similar to other locations of the plant.

Related Element of ASME/ANS PRA Standard

Qualitative Screening (QLS)

Related EPRI 1011989 NUREG/CR-6850 Appendices

None

Supplemental Guidance

There is no supplemental guidance associated with Qualitative Screening (Task 4).